High Speed Rail Roadway Overpass
FACTS OF INTEREST
YEAR: 2007
|
|
SPECIFICATIONS:
|
|
LENGTH: |
10,83 kms.
|
KIND OF WORK: |
Double track of UIC wide High-Speed Rail Roadway
(Roadway total wide, 14,00 m).
Maximum speed: 350 km/h
Traffic type: Passengers.
| 1 P.A.E.T.: |
Overtaking and parking of trains post (sidetrack) with four tracks and platforms, 2.239,50 m long (section wide variable between 26,7 and 31,7 m).
|
STRUCTURES: |
8 Underpasses
1 Overpass
3 Viaducts:
« Rambla de Suge Viaductl »: 86 m long, 3 spans, 38 m maximum span and 1.204,0 m² area.
« Barranco de los Prados de Segovia Viaduct »: 102,75 m long, 3 spans, 44,75 m maximum span and 1.438,5 m² area.
« Viaducto sobre la Autovía A-35 »: 196 m long, 6 spans, 35 m maximum span and 2.744,0 m² area.
|
CONTRACT BUDGET: 1.322.868,18 € (VAT included)
|
|
ESTIMATED BUDGET TO INVITE CONSTRUCTION TENDERS: 45.935.772,64 € (VAT included)
|
|
PERIOD PROVIDED FOR CONSTRUCTION: 24 months. |
CLIENT: SPANISH MINISTRY OF PUBLIC WORKS. Railroads Administration. |