FACTS OF INTEREST:
YEAR: 2008
|
|
TECHNICAL FEATURES:
|
|
LENGTH: |
7,93 Km
|
KIND OF WORK: |
Divided highway with variable median from 6,50 – 10,00 – 23 m wide and dual two lanes driveways (total width of each driveway 10,50 m).
|
INTERCHANGE: 1 |
« Venta del Alto interchange » : Mixed trumpet/diamond type with a roundabout and five strands.
|
TUNNELS: 2 |
« Venta del Alto tunnel» : Twintube 813,00 m long each one and two transverse connection corridors. Excavation realized by means of explosives in 2 stages. Covering consists of bolts, sprayed concrete lining and metal trusses (Austrian Method).
« Tunnel under CN-433 » : Twintube 65,00 m long each one.
|
STRUCTURES: |
1 Viaduct over the river « Rivera de Huelva » 315 m long.
7 underpasses and 2 overpasses.
|
CONTRACT BUDGET: 1.129.062,44 € (VAT included)
|
|
ESTIMATED BUDGET TO INVITED TENDERS OF THE WORKS: 46.068.038,30 € (VAT included)
|
|
PERIOD OF EXECUTION OF WORKS: 29 months. |
CLIENT: Spanish Ministry of Public Works. General Management of Roads. |