Control and Surveillance of the Platform Works of the High Speed Line Madrid – Zaragoza – Barcelona – French Border. Section: Maçanet – Riudellots. Subsection: Sils – Riudellots. File: PC 008/01

Date: 2009
CONTRACT BUDGET: 1.624.662,18 € (V.A.T. included)
BUDGET FOR THE WORKS: 37.299.380,64 € (V.A.T. included)
Client: Gestor de Infraestructuras Ferroviarias (G.I.F.) Currently Administrador de Infraestructuras Ferroviarias (ADIF).

TECHNICAL CHARACTERISTICS:

LENGTH:7.27 kilometers.
WORK CLASS:Platform of High Speed Line of double track of UIC width (Total width of platform, 14.00 m).
Maximum speed : 350 Km/h
Type of traffic : Passengers.
1 P.A.E.T.:Train overtaking and parking station (Girona -Airport siding) for four tracks and platforms, 2,132.85 m long (platform width varying between 26.7 and 31.7 m).
STRUCTURES: 2 Underpasses, 3 Overpasses and 2 Triarched Vaults.
3 Viaducts and expansion of 1 Viaduct:
“Viaduct of the Riera de Vallcanera. “Length 38 m, 1 span and surface 532.0 m².
“Viaduct of the Riera de Bagastrá ” : Length 168 m, 6 spans, maximum span 30 m and surface area 2,352.0 m².
“Viaduct of the Riera de l’Onyar ” : Length 57 m, 3 spans, maximum span 25 m and surface area 798.0 m².
“Extension of the Viaduc de l’Onyar ” : Extension of the length of the deck with an additional 30 m span.
of light, total length of the viaduct 87 m, extended area 420 m² and total area 1,218.0 m².
EXPERIMENTAL SECTION:Construction of a 1.10 km long experimental section consisting of sub-ballast construction.
10 cm thick with hot bituminous mixture

ESTIMATED TIME FOR EXECUTION OF WORKS: 58 months