TECHNICAL CHARACTERISTICS OF THE AUDITED SUBSECTION: | |
LENGTH: | 3.30 kilometers. |
WORK CLASS: | Platform of High Speed Line of double track of UIC gauge. Maximum speed : 350 km/h Type of traffic : Travellers |
TUNNELS: 2 | “La Garriga Tunnel ” 758 m long. Excavation carried out by the advance-cutting method. “Tunnel of Sant Andreu ” of 649 m in length. Excavation carried out by the advance-cutting method. 4 false tunnels, 36.48, 41.52, 40.77 and 43.07 m long. |
STRUCTURES: | 3 Viaducts: “Viaduct over the C-66 highway”: Length 287 m, 6 spans, maximum span 65 m and surface area 4,018 m². “Viaduct Torrent de Riudellots ” : Length 164 m, 5 spans, maximum span 37 m and surface area 3.296 m². “Viaduct Torrent de Marmanyà ” : Length 127 m, 4 spans, maximum span 37 m and surface 1.778 m². |
TIME FOR EXECUTION OF THE WORKS: 50 months.